Body of water meandering through area filled with trees. on the shore are rock formations protruding into the water.
Rock barbs anchor the natural channel design solution, protruding upstream to divert the fastest part of the water flow away from the bank. (Image courtesy of Freese and Nichols)

By Robb Otey, P.E., PACP, M.ASCE, and Nick Lester, P.E.

A swift change of plans and quick collaboration helped prevent wastewater from polluting the Trinity River near Fort Worth, Texas. The result also provided a more natural environment for fish and wildlife.

In late 2019, Fort Worth, Texas, faced a potential environmental and public safety crisis.

Years of erosion along a critical section of the Trinity River had exposed a 90 in. diameter pipeline that, combined with a parallel pipeline of the same dimension, conveys 150 mgd of wastewater to the city’s Village Creek Water Reclamation Facility. Emergency repairs were needed to stabilize the riverbank and pipeline to prevent wastewater flow from polluting the river. It was imperative to protect the exposed pipeline as well as the parallel pipeline.

A project of this size would typically take a year or more to design, permit, advertise/bid, and award. But it was clear that the city did not have that much time to get a solution in place. A plan from 2016 to address the erosion was in hand but had not been constructed; the plan was also no longer sufficient because the river had continued to erode the bank since the plan’s development.

The city decided to bring in a Freese and Nichols team with specialized expertise in riverbank repair to devise a different approach — and quickly.

A multidisciplinary team of engineers and scientists fast-tracked a new design in just three months — and the partners involved in the project overcame unexpected construction challenges to prevent an environmental hazard and keep wastewater services operating while improving river conditions for the long term.

Background

The Trinity River has the distinction of having the largest basin in Texas with a watershed located entirely within the state, and it is an essential natural element for the cities of Fort Worth and Dallas. The Trinity’s West Fork runs mostly west to east across the middle of Fort Worth toward Dallas and feeds several lakes that provide drinking water for residents.

The twin 90 in. mains that convey wastewater to the VCWRF in the far east section of Fort Worth run parallel to the West Fork for several miles, buried in the riverbank. The VCWRF processes 166 mgd of wastewater, serving more than 880,000 people in Fort Worth and 22 neighboring communities as well as numerous industrial customers.

Sheet-pile wall collapses near streambank
The risk of a disaster increased during construction when a section of the temporary sheet-pile wall collapsed, causing part of the exposed pipe to fail. (Image courtesy of Freese and Nichols)

The factors that created the wastewater emergency developed over several years. The city initiated action in 2016 after Fort Worth Water Department field operation crews recognized that record rains from the previous year — including almost 17 in. in May 2015 in the Fort Worth-Dallas area — had set in motion perilous riverbank damage. The erosion brought the river precariously close to the twin pipelines in a largely industrial area, exposing a section of the pipeline nearest to the river and threatening the pipeline farther inland.

At that time, the city hired a consultant to design an emergency bank stabilization and a contractor to make the repairs, but that effort stalled when a cultural resource was discovered at the construction site. The U.S. Army Corps of Engineers, which must approve any work on the Trinity River, required a cultural resources investigation. Bank repairs were suspended for more than a year for a cultural resources survey and report to be completed. (Later, the Corps permit would have to be modified and updated to accommodate a more extensive project scope because the repair needs changed.)

After the delay, the Fort Worth City Council authorized Humphrey & Morton Construction Co. to construct a traditional solution — an anchored footing and sloped rock gabion baskets — to stabilize the streambank. But as this was under construction, more than 28 in. of rain soaked the region in fall 2018. The swelling and receding water caused the river to keep altering its course, exacerbating the erosion. To reinforce the bank and temporarily protect the pipelines, the city instructed Humphrey & Morton to install an additional steel sheet-pile cutoff wall with anchored tiebacks.

After the delay, the Fort Worth City Council authorized Humphrey & Morton Construction Co. to construct a traditional solution — an anchored footing and sloped rock gabion baskets — to stabilize the streambank. But as this was under construction, more than 28 in. of rain soaked the region in fall 2018. The swelling and receding water caused the river to keep altering its course, exacerbating the erosion. To reinforce the bank and temporarily protect the pipelines, the city instructed Humphrey & Morton to install an additional steel sheet-pile cutoff wall with anchored tiebacks.

It soon became clear that the continued erosion was severe enough that the wall with gabion baskets would no longer solve the problem. The city then enlisted Freese and Nichols for a different approach because of the firm’s expertise in geomorphology, structural design, geotechnical analysis, and utility design and its ability to quickly handle all the necessary designs in-house.

A new solution

The Freese and Nichols design team was challenged to prevent environmental damage in a sensitive section of the river where the fragile streambank could not sustain a traditional solution. The riverbank had eroded so much that it was not possible to stabilize the bank and maintain cover over the pipelines. But those constraints actually led to a more ecologically friendly, less expensive approach than otherwise might have resulted.

Photo shows how a crew repaired the damaged pipelines
Bank stabilization work stopped while a 340 ft section of one of two 90 in. diameter pipelines was repaired. To keep the system and public services running without interruption during the repair, a 10-pump bypass system, shown in the background, diverted the wastewater from the damaged pipe to its intact twin. (Image courtesy of Freese and Nichols)

The design team began by using geomorphology to evaluate where the river might migrate over the next 50-100 years. Using aerial photographs, team members mapped historic bank lines and estimated future river migration, determining that the West Fork’s northeast movement would erode the streambank upstream of the problem area. That meant the repairs would need to be made farther upstream of the damaged section to maximize their longevity.

The conditions also created a situation well suited to a natural channel design approach that could restore the riverbank and maximize its function more sustainably for the long term. Natural channel design aims to restore a stream and its banks so it can maintain a natural state of stability with less reliance on excavation and bank armoring to manage the water flow.

The design revolved around three key elements:

  • Rock barbs: These protrude upstream and divert the fastest part of the water flow away from the bank. Using these structures reduced the amount of excavation needed along the bank to guard against scour damage underneath the rock. This reduced the construction footprint on the river and saved the city on excavation costs. In addition, pools that form around the barbs provide attractive habitat for fish.
  • Launchable rock toes: When scour occurs, a hole is formed by the fast-moving water, removing native material from the riverbed and undermining the riprap above. The launchable rock toes were designed to slump into the scour holes while protecting the shape of the uphill portion of the strengthened streambank.
  • Concrete terrace wall: Because of the proximity of the wastewater lines to the river, there was not enough room for a stable slope to be created. So the engineers designed a hybrid system with a combination of a vertical reinforced-concrete wall with slopes above and below it. A strategically located 430 ft long wall of varying heights was to be founded on a line tangential to the drilled shafts.

Two additional features of the design underscore the environmentally beneficial nature of the solution:

  • Willow stakes: Live saplings were driven into gaps in the rocks. Though dormant when installed, the trees will eventually sprout and grow, adding greenery and improved aquatic health along the bank. Their roots will also increase the cohesive strength of the bank, providing long-term stability.
  • Flood protection: Because the area lies within a floodway defined by the Federal Emergency Management Agency, the repairs had to avoid increasing the degree of rise of the river because to do so would alter its 100-year flood capacity. The design met this requirement by minimizing the material needed for construction.

The Corps granted a permit for this new design in March 2020. This marked the first time that the Corps’ Fort Worth District had permitted rock barbs.

Another emergency

This design needed to be implemented promptly. But with a quarter of construction completed, an urgent situation emerged that called for an agile, creative response. Another wet spring had saturated the construction site. In June 2020, while piers for the proposed terrace wall were under construction (overseen by Humphrey & Morton), a 200 ft section of the temporary sheet-pile wall that was shielding the pipes from the river collapsed, and a section of the exposed pipeline shifted. This meant a wastewater leak into the river was imminent.

Map that shows historic streambank lines in different years
STREAMBANK MIGRATION (Map courtesy of Freese and Nichols)

Freese and Nichols brought in a team of its staff who were experienced in utility, structural, stormwater, and geotechnical designs. Working with construction inspection personnel, the group developed a method for restoring the sheet-pile wall by cutting a V notch along its midsection, bending it back on itself, and welding it in place.

In conjunction with Xylem, a dewatering company, the engineers established a bypass system using 10 pumps to divert flow around the section of pipe that had failed. This meant that the pipeline that was farther from the river was doing the work of both mains for several months. This allowed wastewater service to continue uninterrupted while the contractor, Circle C Construction Co., removed and replaced a 340 ft section of the damaged pipe so the bank stabilization construction could resume.

During this critical stage after the sheet-pile wall collapse, Xylem provided around-the-clock observation, while Freese and Nichols committed more than a dozen engineers, many of them principals in the firm, to make sure all options were considered and all needed resources were available. All repairs along the river were substantially completed by March 2021.

Lessons learned

Restoring a damaged riverbank can be complicated, challenging, and risky. Undertaking it in a way that minimizes the impact on the river requires specialized knowledge and training. This project had the additional complications of a construction emergency, extra safety precautions, and schedule juggling necessitated by the coronavirus pandemic.

It took engineers and scientists with expertise in geomorphology, structural design, wastewater systems, natural channel design, environmental permitting, and emergency project management, who partnered with the Fort Worth Water Department, other city staff, and multiple construction teams to implement the solution.

Some of the key takeaways from the experience that may be instructive for other engineers are:

  • Capitalize on opportunities to innovate. The riverbank damage left so little area to work with that building a tall wall, which was the city’s original approach and might typically have been the first choice, was not feasible. Natural channel design offered an alternative restoration approach that addressed the environmental sensitivity of the locale and the space constraints. Using these techniques showed how pipelines can be protected within a body of water’s erosion hazard zone and a problem can be solved using natural dynamics instead of trying to bend nature to human will.
  • Anticipate openings for time savings. The repairs had to be completed as soon as possible. While a specific schedule was not defined in this case, steps were taken to accelerate the process. All parties understood that condensing the construction schedule would reduce construction costs and limit the risk of a catastrophic failure. During the embankment construction, access maintenance holes for bypass suction piping were constructed in case of a failure that required a bypass system. This reduced setup time when a failure did occur and bypass pumping was needed. During the pipeline replacement, new pipe was ordered concurrent with design to reduce construction time. And weekly meetings helped monitor progress and resolve issues.
  • Prepare for infrastructure emergencies. With forward-looking processes, cities can reduce risks and be ready to act quickly. Regularly monitor municipal infrastructure that has been installed in water bodies’ erosion hazard zones. Anticipate problems and streamline administrative steps that will be required. For example, have emergency contracts in place with utility contractors and bypass pumping contractors; be able to execute emergency contracts as soon as possible when needed.
  • Conduct a risk analysis and consequence of failure study, especially on larger and nonredundant assets, and develop a contingency plan in case a key structure becomes temporarily unusable.

Since the construction was completed, both pipeline sections have been operating without the erosion issues, thanks to the repairs. The solution also meant that flood risk along the river was reduced, while the fish and wildlife are expected to thrive. Monitoring will be ongoing to verify that everything is performing as intended.

The city is working with Freese and Nichols in other areas along the river to protect additional water and wastewater lines from erosion. 

Robb Otey, P.E., PACP, M.ASCE, is an associate and senior project manager, and Nick Lester, P.E., is a vice president/principal and group manager for water/wastewater transmission and utilities for Freese and Nichols.

Project Credits

Owner: Fort Worth (Texas) Water Department
Geomorphology, structural design, geotechnical analysis, and utility design: Freese and Nichols, Fort Worth
Permitting agency: U.S. Army Corps of Engineers, Fort Worth District 
Contractor (steel-pile cutoff wall, concrete wall, and riprap embankment): Humphrey & Morton Construction Co., Fort Worth
Contractor (pipeline repair): Circle C Construction Co., Fort Worth
Contractor (bypass pumping): Xylem, Rye Brook, New York

This article first appeared in the May/June 2022 issue of Civil Engineering as “Protecting the Trinity.”